Subdomain 1.2: Lean principles in the organization
1.A bakery operates 480 minutes per day and customers demand 240 loaves per day. What is the takt time?
- A.2 minutes per loaf
- B.1 minute per loaf
- C.0.5 minutes per loaf
- D.4 minutes per loaf
Show answer & explanation
Correct answer: A — 2 minutes per loaf
- A. This is correct. Dividing the 480 available minutes by the 240 loaves of daily demand gives a takt time of 2 minutes per loaf, meaning the bakery must complete a loaf every 2 minutes to keep pace with demand.
- B. This would result from dividing demand by available time or from an arithmetic error, but it does not match 480 divided by 240.
- C. This value is too fast for the given numbers and would only be correct if demand were 960 loaves per day, which is not the case here.
- D. This value is too slow for the given numbers and would only be correct if demand were 120 loaves per day, which is not the case here.